PJM Queue — Note 007

What the five findings do when you put them together.

What the five findings do when you put them together.

Kenneth · 2026-08-12

Source: LBNL Queued Up 2026 Edition (CC BY 4.0), through end-2025. Analysis my own.


Six notes, each with one finding. Held apart they are interesting. Multiplied

together they change what a queue position is worth.

NoteFinding
001The 68% composite hides a 34–98% spread by technology
002It rose from ~68% pre-2014 to 93% for 2018–21
003Not PJM — 16 of 19 operators worsened. ERCOT went the other way
004Time to build roughly doubled: 1.5 years to 5.0
005Failure rises with size: 76% under 20 MW, 89% at 100–299 MW
006Battery converts at 0.5% of requested MW. Offshore wind at 0.0%

Worked example — a 150 MW battery filed in PJM today

Take the base rates as they stand rather than the composite:

Every axis points the same way, and they are not independent — a large recent

battery is in the worst bucket of all four. A defensible planning assumption is

below one in ten, against a composite figure of roughly one in three.

The same project at 40 MW, in ERCOT, is a different business. Note 005 says

small does better; Note 003 says ERCOT converts at 61% failure against PJM's 93%.

Neither of those is a small adjustment.

What this is not

It is not a model. These are base rates from history, multiplied by

inspection rather than by regression. A real underwriting model would need

interconnection costs, upgrade allocations and developer identity, none of which

this dataset carries.

What it is: a much better prior than 68%, and a demonstration that the number

everyone quotes is wrong in at least four independent directions at once.


*Method: every figure traceable to Notes 001–006, each a count from the published

LBNL file. Free at emp.lbl.gov/queues.*

*This is published research. Every figure is a count from a free dataset at emp.lbl.gov/queues — check it yourself rather than taking my word for it.